Construction Timeline Phase 1

Targeted timeline is subject to change.

  • Cleaning Out of Existing Buildings: December 22, 2025 - January 5, 2026

  • Environmental Abatement of Existing Building: January 5, 2026 – extended to February 5, 2026

  • Demolition of Existing Building (Restaurant & Market at Capp St & 16th St): February 6th – February 27, 2026

    • Please note: Building demolition will be performed from the top down in sections, and no dynamite or explosives will be used as part of this work. Throughout the demolition process, water will be continuously applied to help mitigate dust and airborne particles. In addition, air monitoring devices have been installed around the construction site to monitor and regulate air quality during active work.

  • Construction Period: March 2, 2026 – December 6, 2027

  • Leasing and Occupancy: Begins March 7, 2027

[Español] Cronograma de Construcción Fase 1

El cronograma previsto está sujeto a cambios.

  • Limpieza de los Edificios Existentes: 22 de diciembre del 2025 – 5 de enero del 2026

  • Remediación Ambiental de Estructuras Existentes: 22 de diciembre del 2025 – prorrogado hasta el 5 de febrero del 2026

  • Demolición de Estructuras Existentes (Restaurante y Mercado en las calles Capp y 16): 6 de febrero del 2026 – 27 de febrero del 2026

    • Tenga en cuenta lo siguiente: la demolición del edificio se realizará de arriba abajo, por secciones, y no se utilizará dinamita ni explosivos. Durante todo el proceso de demolición, se aplicará agua de forma continua para minimizar el polvo y las partículas en suspensión. Además, se han instalado dispositivos de monitorización del aire alrededor de la obra para controlar y regular la calidad del aire durante los trabajos.

  • Periodo de Construcción: 2 de marzo del 2026 – 6 de diciembre del 2027

  • Arrendamiento y Ocupación: Comienza el 7 de marzo del 2027

Para obtener más detalles, haga clic en el botón de abajo para ver una presentación de diapositivas.

Contact Persons / Personas de Contacto:

  • Carlos Melgoza, cmelgoza@missionhousing.org

  • Steve Fisher, Sr. Superintendent, sfisher@guzmangc.com

  • Filiberto Diaz, Project Manager, fdiaz@guzmangc.com

December 2025 - Message from our General Contractor, Cahill & Guzman JV Team:

You will see increased activity around the site as we prepare to demolish the current buildings and begin construction. We just started construction operations on Monday, December 22.

During this initial phase of the work, we will be:

  • Installing new fence panels around the 2970 16th Street site (corner of 16th and Capp Streets).

  • Delivering tools/materials. 

  • Installing air monitoring devices. 

  • Starting abatement work

Some additional items for reference or to be noted are as follows:

  • The construction activity schedule will typically be from 7 AM to 3 PM.

  • We do not anticipate any work on a Saturday or Sunday in December.  We will notify neighbors of any future weekend work. 

  • Security cameras will be present 24/7. 

  • A security guard will be present throughout the week. 

[Español] Diciembre 2025 - Mensaje de nuestro contratista general, el equipo conjunto de Cahill & Guzman:

Observarán una mayor actividad en los alrededores del sitio del proyecto a medida que nos preparamos para demoler los edificios actuales e iniciar la construcción. Comenzamos las obras de construcción el lunes 22 de diciembre. Durante esta fase inicial de los trabajos, realizaremos las siguientes tareas:

  • Instalación de cercas y vallas alrededor del sitio en 2970 16th Street (esquina de las calles 16 y Capp).

  • Descarga de herramientas y materiales.

  • Instalación de dispositivos de monitoreo de la calidad del aire.

  • Inicio de los trabajos de descontaminación.

Otros puntos importantes para tener en cuenta:

  • El horario de las actividades de construcción será típicamente de 7 AM a 3 PM.

  • No se prevé realizar trabajos los sábados ni los domingos de diciembre. Informaremos a los vecinos sobre cualquier trabajo que se realice en fin de semana en el futuro. 

  • Habrá cámaras de seguridad las 24 horas del día, los 7 días de la semana.

  • Un guardia de seguridad estará presente durante toda la semana.